Personnel On-Scene: 07/12/08 START-1, ERRS-8, Security-1 (24 hr) 07/14/08 EPA-1, PADEP-2, START-1, ERRS-8, Other-3, Security-1 (24 hr) Weather: 07/12/08 Low of 69° F, high of 88° F Partly Cloudy, 0.00inches of precipitation, wind Variable 4-8 mph. 07/14/08 Low of 55° F, high of 81° Clear, 0.00inches of precipitation, W 5-10 mph.
07/12/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental, Inc held its morning safety meeting and discussed the days planned activities. ERRS continues to repackage drums of magnesium to be shipped off site at a later date. ERRS repackaged 101 drums for the day.
START assisted as needed and conducted written/photographic documentation. START demobilized.
07/14/08 USEPA OSC Jack Downie was on site for oversight of activities.
PADEP Mariruth Hoffman mobilized to site and assisted the EPA in oversight. PADEP Hoffman demobilized.
Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental, Inc held its morning safety meeting and discussed the days planned activities. ERRS continued repackaging material from non-DOT shippable drums into 55-gallon vented DOT shippable drums. ERRS repackaged 126 drums for the day. START mobilized to site and assisted the EPA as needed and conducted written/photographic documentation.
|