POLLUTION REPORT
|
| Date: |
Friday, August 8, 2008
|
| From: |
Jack Downie
|
| To: |
Daniel Taylor, EPA
|
RRC RRC, EPA
|
|
Mariruth Hoffman, PA DEP
|
Bryan Werner, PA DEP BRP
|
|
Subject:
|
Removal Action
Remacor, Inc.
P.O. Box 366,
West Pittsburg, PA
Latitude: 40.9349711 Longitude: -80.3686583
|
| POLREP No.: |
170
|
Site #:
|
G3GM
|
| Reporting Period: |
8/7/08 to 8/8/08
|
D.O. #:
|
03-04-015
|
| Start Date: |
9/15/2006
|
Response Authority:
|
CERCLA
|
Mob Date: |
9/15/2006
|
Response Type:
|
Emergency
|
| Demob Date: |
|
NPL Status:
|
Non NPL
|
| Completion Date: |
|
Incident Category:
|
Removal Action
|
| CERCLIS ID #: |
PAD074965096
|
Contract #
|
|
| RCRIS ID #: |
|
|
|
EPA is continuing emergency removal actions at this site during the repackaging, transportation, and removal of flammable magnesium materials. Lavigne Manufacturing, Inc. is making plans to remove its material off site. EPA continues to plan and implement repackaging of magnesium materials to make it more stable and accessible for the remainder of the generators who wish to remove their material.
The ERRS contractor is repackaging the remainder of drums on site. PADEP is providing technical and oversight support at the site. The EPA START contractor TechLaw is providing technical and administrative support to the EPA. EPA and PADEP officials continue to control access to the site in addition to coordinating the activities of the various generators.
|
|
Personnel On-Scene: 8/7/08 EPA-2, START-2, ERRS-8, Other-1, Security-1 (24 hr) 8/8/08 START-1, ERRS-9, Other-1, Security-1 (24 hr) Weather: 08/07/08 Low of 59° F, high of 79° F, clear to mostly cloudy, 0.00 inches precipitation, wind NW 3-14 mph. 08/08/08 Low of 54° F, high of 74° F, clear to mostly cloudy, 0.12 inches precipitation, wind NW 2-18 mph.
08/07/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities. ERRS repackaged 88 drums and staged them in Building #2. A total of 1,705 drums have been repackaged and staged in Building #2. ERRS conducted maintenance and house-keeping activities on site as required.
START provided technical assistance, contractor oversight, written and photographic documentation during field activities.
08/08/08 Emergency and Rapid Response Services (ERRS) contractor Guardian Environmental Services, Inc. held its morning safety meeting and discussed the days planned activities. ERRS repackaged approximately 90 drums and staged them in Building #2. ERRS conducted maintenance and house-keeping activities on site as required.
START provided contractor oversight, written/photographic documentation and technical assistance during ongoing activities.
|
| |
Budgeted |
Total To Date |
Remaining |
% Remaining |
|
Extramural Costs
|
| ERRS - Cleanup (thru 9/9/07) |
$575,000.00 |
$491,435.00 |
$83,565.00 |
14.53% |
| ERRS - Cleanup (9/10/07 to Present) |
$3,025,000.00 |
$2,494,028.00 |
$530,972.00 |
17.55% |
| RST/START |
$482,980.00 |
$332,269.00 |
$150,711.00 |
31.20% |
|
Intramural Costs
|
| |
| Total Site Costs |
$4,082,980.00 |
$3,317,732.00 |
$765,248.00 |
18.74% |
* The above accounting of expenditures is an estimate based on figures known to the OSC at the time this report was written. The OSC does not necessarily receive specific figures on final payments made to any contractor(s). Other financial data which the OSC must rely upon may not be entirely up-to-date. The cost accounting provided in this report does not necessarily represent an exact monetary figure which the government may include in any claim for cost recovery.
response.epa.gov/remacor
POLREP #170 Last Updated 8/12/2008
|