Old Sawmill
Asbestos Site Update
US Environmental
Protection Agency
September 1-7, 2024
Current
Situation
Site
Description: The EPA Region 9
Removal Program is conducting a Time Critical Removal Action (TCRA) at the Old
Sawmill Asbestos Site, Navajo Nation, Sawmill, AZ. This action began the week of September 1,
2024.
This removal action is being performed by U.S.
EPA to mitigate the release or threat of release of hazardous substances that
is causing a threat to public health and the environment by taking steps to
prevent the ongoing release of asbestos fibers.
The goal is to complete work this field
season, which will take around 6 weeks.
Removal Objectives:
- Protect worker and community health and safety.
- Ensure all response actions are consistent with the National Contingency Plan.
- Keep stakeholders including community informed of response actions.
- Remove all or portions of the former concrete kiln building.
- Remove visible asbestos-contaminated soil or material from the area surrounding the former concrete kiln building and other demolished buildings on Site.
- Utilize dust suppression/wetting techniques to prevent a release.
- Conduct air and soil sampling to demonstrate that the hazards have been mitigated and to document that dust suppression techniques are effective.
- Transport and dispose of removed/excavated material at an appropriate facility in compliance with the off-site rule, 40 CFR § 300.440
- Conduct confirmation sampling and analysis where the former kiln building was demolished.
Current Actions / Progress to Date
Mobilized to Site on 9/3/2024
Received equipment on site all week,
including heavy equipment, rock, trailers, and water tanks.
Set up water tank holding and dispersal
system, which consists of 4 tanks and 500 feet of hoses for dust suppression.
Continued collecting water from the Navajo
Water Resource Lagoon and started dust suppression activity.
Surveyed site around the kiln building for
visible asbestos and marked with pink spray paint. Not all areas could be inspected due to heavy
vegetation.
Began removing dispersed asbestos debris
on soil.
Began installation of perimeter fencing.
Collected background air monitoring and
sampling data prior to work starting.
Set up 7 dust trac monitoring stations (3
around the Site perimeter and 4 in the surrounding community) to take daily
particulate measurements as well as air samples.
ACM Contaminated Material Removed: Trucks 0
Planned
Actions
- Continue air monitoring and sampling.
- Continue dust suppression during removal action.
- Demolish the former kiln building.
- Remove visible asbestos from the soil surrounding the kiln building.
- Haul asbestos containing material/demo debris to disposal facility.
- Regrade disturbed areas.
Organization
The EPA Region 9 Removal Program is conducting
this removal action. Stakeholder
communication is being shared with Navajo EPA, Navajo F&W, Sawmill Chapter
Officials, and the Community.
Resources
On-Site
Personnel on-site include: EPA On-Scene Coordinator (1-2 OSCs), Crew of
Environmental Quality Management and Subcontractors (ERRS 10-12), and Weston
(2-3)
Community
Involvement Activities
Recent
Actions:
A Chapter House/Community meeting took
place in August 2024.
Planned
Actions:
OSCs will
present at the Chapter House meeting on 9/9/24 and the first week of October. Weekly site updates will be posted to the
website and shared with stakeholders.
Website
https://response.epa.gov/oldsawmillasbestos